Getting paid on public contracts: the 30-day rule for contractors and subcontractors
On this page (10 parts)
Public work does not always pay on time. Delays can come from invoices that are rejected or disputed, or from main contractors who are slow to pay their supply chain. The Procurement Act 2023 puts a 30-day payment term into most public contracts in England, Wales and Northern Ireland, and into the subcontracts that help deliver them. This guide explains how it works and what to do when money is late.
Key points
- Under section 68 of the Procurement Act 2023, most public contracts carry an implied term that valid, undisputed invoices are paid within 30 days. A contract term that tries to override it has no effect.
- Section 73 implies the same term into "public sub-contracts", so a subcontractor on a public job should also be paid within 30 days.
- The terms also apply to regulated below-threshold contracts and their subcontracts, but not to contracts awarded by schools, concession contracts, contracts awarded by private utilities, utilities contracts below the threshold (whoever awards them), or below-threshold contracts awarded by most Northern Ireland public bodies.
- If a buyer disputes an invoice or considers it invalid, the 30 days do not run, but it must tell you without undue delay.
- When payment is late you can claim statutory interest and fixed recovery costs, and raise a concern with the Public Procurement Review Service.
What the 30-day rule says
Section 68 says any sum due under a public contract must be paid within 30 days, counted from the later of the day the buyer receives the invoice and the day payment falls due under the invoice. The parties can agree to pay sooner, but not later. The Cabinet Office guidance on electronic invoicing and payment adds that payment "must be made before the end of day 30", and that using supply chain finance to reduce the amount paid would not comply.
The same guidance confirms that section 88 of the Act implies the section 68 and 73 terms into regulated below-threshold contracts and their subcontracts, so the rule covers the smaller council and NHS jobs many trades firms win first.
| Contract | 30-day term implied? |
|---|---|
| Public contract under the Act (above threshold) | Yes, section 68 |
| Regulated below-threshold contract | Yes, section 88 |
| Subcontract that helps deliver either of the above | Yes, section 73 |
| Contract awarded by a school | No |
| Concession contract, or utilities contract awarded by a private utility | No |
| Utilities contract below the threshold, whoever awards it (not a regulated below-threshold contract, section 84) | No |
| Below-threshold contract awarded by a transferred Northern Ireland authority (most NI public bodies) | No |
Procurements that started before 24 February 2025 continue under the old rules, so check the payment clause in those contracts.
What makes an invoice valid
The clock only runs on a valid invoice. Under section 68, an invoice is valid if it is an electronic invoice in the required format, or if it meets any requirements in the contract and contains at least:
- your name as the invoicing party;
- a description of the goods, services or works;
- the sum requested;
- a unique identification number.
Many buyers add contract requirements, such as a purchase order number or a named invoicing system. Where the contract names an invoicing system, the clock starts on the day the invoice is received onto that system, so read the invoicing clause before your first invoice, quote the purchase order number every time, and keep proof of when each invoice was sent.
Disputed invoices
The 30 days do not apply if the buyer disputes the invoice or considers it invalid, but it must tell you "without undue delay". If you learn weeks later that an invoice was rejected, ask when and why. The guidance recommends that contracts set out how invoice disputes are resolved, so follow your contract's dispute clause.
If you are a subcontractor
Section 73 defines a public sub-contract as a contract substantially for the purpose of performing, or contributing to the performance of, all or part of a public contract. If you service fire alarms or clean offices under a main contractor's public contract, your subcontract is likely to be one. That has two effects:
- Longer terms do not bite. A clause in your subcontract saying you will be paid in 60 days has no effect where section 73 applies; the 30-day term is implied instead.
- The clock starts from your invoice. The guidance says suppliers must pay relevant subcontractors within 30 days of receiving the subcontractor's invoice, or by any later due date set in that invoice.
Before you sign, ask the main contractor which public contract the work is for.
How payment performance is checked
The rules come with reporting that gives you evidence if things go wrong:
- Payments compliance notices. Most contracting authorities must publish a notice every six months on the Central Digital Platform showing their average days to pay and the percentage of invoices paid within 30 days. The duty came into force on 1 January 2026 (1 April 2026 for procurement regulated by the Welsh Ministers), and the first notices had to be published between 31 March and 29 April 2026 (GOV.UK). Schools, private utilities and transferred Northern Ireland authorities are exempt (GOV.UK guidance).
- Spot checks on subcontract payments. Under PPN 021, central government departments, their agencies and non-departmental public bodies should spot check that suppliers on contracts worth over £5 million a year (including VAT) are meeting the 30-day term in their subcontracts, at least every six months, for contracts advertised from 1 October 2025.
- Payment record at bid stage. Under PPN 018, the same bodies assess bidders for contracts over £5 million a year on whether they pay at least 95% of invoices within 60 days (90% with an action plan) and within 45 days on average. That gives main contractors a reason to pay their supply chain promptly.
What to do when payment is late
First check the invoice was valid and went to the right place. Then chase in writing, referring to the 30-day term in the contract or to section 68 or 73 of the Act. If that does not work, you have three further options.
Interest and costs. Under late payment law, you can claim interest at 8% plus the Bank of England base rate on business debts unless your contract sets a different rate, and a contract with a public authority cannot set a lower rate. You can also claim a fixed sum once per late payment: £40 for debts under £1,000, £70 for £1,000 to £9,999.99, and £100 for £10,000 or more.
Public Procurement Review Service. The service looks at late payment of valid, undisputed invoices, including in the supply chain, on contracts let by in-scope authorities such as central government, councils, emergency services and health bodies. You can ask to stay anonymous when it contacts the buyer, and the issue must have happened in the last two years. It does not cover devolved Scottish, Welsh or Northern Ireland authorities, private utilities or schools buying directly, its recommendations are not binding, and it suspends its involvement if you start legal action, including sending a pre-action letter (scope and remit).
Small Business Commissioner. If you have fewer than 50 employees and a large UK business (more than 50 employees), such as a main contractor, owes you money, the Office of the Small Business Commissioner can consider a complaint about payment, usually where payment was due within the last 12 months. It does not handle construction disputes or work covered by the Housing Grants, Construction and Regeneration Act 1996: for those, use adjudication (see our guide to subcontracting on public contracts).
Scotland
Devolved Scottish public bodies are largely outside the Act, but the Scottish Government requires its suppliers to be paid within 30 days of a valid invoice, and requires main suppliers to pay subcontractors within 30 days at all stages of the supply chain, according to the Scottish Government's Supplier Journey guidance.
Changes on the way: the Commercial Payments Bill
The Commercial Payments Bill was introduced to Parliament in May 2026 and, on 13 November 2026, was in the House of Commons. It is not law yet, and the rules above still apply. According to the government's overview, it would:
- cap payment terms between businesses at 60 days, with strictly limited exemptions;
- ban deducting and withholding retentions under construction contracts, with the timing still to be consulted on;
- give suppliers a right to a fixed sum where a purchaser raises a dispute late or without enough information;
- give the Small Business Commissioner powers to adjudicate payment disputes between small and larger businesses, and to investigate and fine persistent poor payers.
For subcontractors on public contracts this would sit alongside the 30-day rule, which already applies down the supply chain. The government says there will be a lead-in period, and the changes will not apply to payments or contracts retrospectively.
Frequently asked questions
Does the 30-day rule apply to small council jobs?
Yes, if the job is a regulated below-threshold contract under the Act, such as a council or NHS contract. It does not apply to contracts awarded by schools, to utilities contracts below the threshold (such as a water or energy company's small jobs), or to below-threshold contracts awarded by most Northern Ireland public bodies.
My main contractor's terms say 60 days. Which applies?
If your subcontract is substantially for performing, or contributing to, a public contract under the Act, the implied 30-day term applies and a term that tries to override it has no effect. Check which contract your work supports and raise it with the contractor in writing.
Can I charge interest to a council?
Yes. Statutory interest applies to late commercial payments from public authorities too.
BidTrowel's contract pages show the buyer and the key facts from each notice, which helps you check what kind of public contract a job sits under.
This guide is general information, not legal advice. Check your contract's payment and dispute clauses, and take advice before starting legal action.
Sources
- UK Parliament: Commercial Payments Bill [HL] (checked 13 November 2026)
- GOV.UK: Commercial Payments Bill overview (checked 13 November 2026)
- legislation.gov.uk: Procurement Act 2023, sections 67 and 68 (terms implied into public contracts) (checked 20 October 2026)
- legislation.gov.uk: Procurement Act 2023, section 73 (payment terms in public sub-contracts) (checked 20 October 2026)
- Welsh Government: Procurement Act 2023 guidance on below-threshold contracts (section 84 definition) (checked 21 October 2026)
- GOV.UK: guidance on electronic invoicing and payment (checked 20 October 2026)
- GOV.UK: guidance on payments compliance notices (checked 20 October 2026)
- GOV.UK: new legislative requirements under the Procurement Act 2023 (checked 20 October 2026)
- GOV.UK: PPN 021, payment spot checks in public sub-contracts (PDF) (checked 20 October 2026)
- Procurement Pathway: PPN 018, a supplier's approach to payment in major contracts (checked 20 October 2026)
- GOV.UK: PPN 018 guidance (PDF) (checked 20 October 2026)
- GOV.UK: late commercial payments, charging interest (checked 20 October 2026)
- GOV.UK: late commercial payments (checked 21 October 2026)
- GOV.UK: late commercial payments, claiming debt recovery costs (checked 20 October 2026)
- GOV.UK: Public Procurement Review Service scope and remit (PDF) (checked 20 October 2026)
- Office of the Small Business Commissioner: FAQs (checked 21 October 2026)
- Supplier Journey (Scottish Government): prompt payment (checked 20 October 2026)