Getting paid on public contracts: the 30-day rule for contractors and subcontractors

Last reviewed 13 November 2026. General guidance, not legal advice.

On this page (10 parts)
  1. What the 30-day rule says
  2. What makes an invoice valid
  3. Disputed invoices
  4. If you are a subcontractor
  5. How payment performance is checked
  6. What to do when payment is late
  7. Scotland
  8. Changes on the way: the Commercial Payments Bill
  9. Frequently asked questions
  10. Sources

Public work does not always pay on time. Delays can come from invoices that are rejected or disputed, or from main contractors who are slow to pay their supply chain. The Procurement Act 2023 puts a 30-day payment term into most public contracts in England, Wales and Northern Ireland, and into the subcontracts that help deliver them. This guide explains how it works and what to do when money is late.

Key points

What the 30-day rule says

Section 68 says any sum due under a public contract must be paid within 30 days, counted from the later of the day the buyer receives the invoice and the day payment falls due under the invoice. The parties can agree to pay sooner, but not later. The Cabinet Office guidance on electronic invoicing and payment adds that payment "must be made before the end of day 30", and that using supply chain finance to reduce the amount paid would not comply.

The same guidance confirms that section 88 of the Act implies the section 68 and 73 terms into regulated below-threshold contracts and their subcontracts, so the rule covers the smaller council and NHS jobs many trades firms win first.

Contract 30-day term implied?
Public contract under the Act (above threshold) Yes, section 68
Regulated below-threshold contract Yes, section 88
Subcontract that helps deliver either of the above Yes, section 73
Contract awarded by a school No
Concession contract, or utilities contract awarded by a private utility No
Utilities contract below the threshold, whoever awards it (not a regulated below-threshold contract, section 84) No
Below-threshold contract awarded by a transferred Northern Ireland authority (most NI public bodies) No

Procurements that started before 24 February 2025 continue under the old rules, so check the payment clause in those contracts.

What makes an invoice valid

The clock only runs on a valid invoice. Under section 68, an invoice is valid if it is an electronic invoice in the required format, or if it meets any requirements in the contract and contains at least:

Many buyers add contract requirements, such as a purchase order number or a named invoicing system. Where the contract names an invoicing system, the clock starts on the day the invoice is received onto that system, so read the invoicing clause before your first invoice, quote the purchase order number every time, and keep proof of when each invoice was sent.

Disputed invoices

The 30 days do not apply if the buyer disputes the invoice or considers it invalid, but it must tell you "without undue delay". If you learn weeks later that an invoice was rejected, ask when and why. The guidance recommends that contracts set out how invoice disputes are resolved, so follow your contract's dispute clause.

If you are a subcontractor

Section 73 defines a public sub-contract as a contract substantially for the purpose of performing, or contributing to the performance of, all or part of a public contract. If you service fire alarms or clean offices under a main contractor's public contract, your subcontract is likely to be one. That has two effects:

  1. Longer terms do not bite. A clause in your subcontract saying you will be paid in 60 days has no effect where section 73 applies; the 30-day term is implied instead.
  2. The clock starts from your invoice. The guidance says suppliers must pay relevant subcontractors within 30 days of receiving the subcontractor's invoice, or by any later due date set in that invoice.

Before you sign, ask the main contractor which public contract the work is for.

How payment performance is checked

The rules come with reporting that gives you evidence if things go wrong:

What to do when payment is late

First check the invoice was valid and went to the right place. Then chase in writing, referring to the 30-day term in the contract or to section 68 or 73 of the Act. If that does not work, you have three further options.

Interest and costs. Under late payment law, you can claim interest at 8% plus the Bank of England base rate on business debts unless your contract sets a different rate, and a contract with a public authority cannot set a lower rate. You can also claim a fixed sum once per late payment: £40 for debts under £1,000, £70 for £1,000 to £9,999.99, and £100 for £10,000 or more.

Public Procurement Review Service. The service looks at late payment of valid, undisputed invoices, including in the supply chain, on contracts let by in-scope authorities such as central government, councils, emergency services and health bodies. You can ask to stay anonymous when it contacts the buyer, and the issue must have happened in the last two years. It does not cover devolved Scottish, Welsh or Northern Ireland authorities, private utilities or schools buying directly, its recommendations are not binding, and it suspends its involvement if you start legal action, including sending a pre-action letter (scope and remit).

Small Business Commissioner. If you have fewer than 50 employees and a large UK business (more than 50 employees), such as a main contractor, owes you money, the Office of the Small Business Commissioner can consider a complaint about payment, usually where payment was due within the last 12 months. It does not handle construction disputes or work covered by the Housing Grants, Construction and Regeneration Act 1996: for those, use adjudication (see our guide to subcontracting on public contracts).

Scotland

Devolved Scottish public bodies are largely outside the Act, but the Scottish Government requires its suppliers to be paid within 30 days of a valid invoice, and requires main suppliers to pay subcontractors within 30 days at all stages of the supply chain, according to the Scottish Government's Supplier Journey guidance.

Changes on the way: the Commercial Payments Bill

The Commercial Payments Bill was introduced to Parliament in May 2026 and, on 13 November 2026, was in the House of Commons. It is not law yet, and the rules above still apply. According to the government's overview, it would:

For subcontractors on public contracts this would sit alongside the 30-day rule, which already applies down the supply chain. The government says there will be a lead-in period, and the changes will not apply to payments or contracts retrospectively.

Frequently asked questions

Does the 30-day rule apply to small council jobs?

Yes, if the job is a regulated below-threshold contract under the Act, such as a council or NHS contract. It does not apply to contracts awarded by schools, to utilities contracts below the threshold (such as a water or energy company's small jobs), or to below-threshold contracts awarded by most Northern Ireland public bodies.

My main contractor's terms say 60 days. Which applies?

If your subcontract is substantially for performing, or contributing to, a public contract under the Act, the implied 30-day term applies and a term that tries to override it has no effect. Check which contract your work supports and raise it with the contractor in writing.

Can I charge interest to a council?

Yes. Statutory interest applies to late commercial payments from public authorities too.

BidTrowel's contract pages show the buyer and the key facts from each notice, which helps you check what kind of public contract a job sits under.

This guide is general information, not legal advice. Check your contract's payment and dispute clauses, and take advice before starting legal action.