What is a PQQ, and what replaced it?

Last reviewed 19 October 2026. General guidance, not legal advice.

Many trades firms still talk about "doing a PQQ", and some buyers and main contractors still send documents with that name. Officially, though, the pre-qualification questionnaire was replaced in 2016 by the Standard Selection Questionnaire (SQ), and for most new public procurements in England, Wales and Northern Ireland the SQ has itself been replaced under the Procurement Act 2023. This guide explains what each one is, what you will see now, and what to have ready so you can answer any version quickly.

Key points

What a PQQ was

A pre-qualification questionnaire asked suppliers about their business before the buyer decided who could tender. Typical questions covered company details, financial standing, insurance, health and safety, quality management, equality, environmental management and past experience. Buyers used the answers to remove unsuitable firms and shortlist the rest.

The problem for small firms was repetition and cost. Each buyer had its own version, so the same information had to be supplied again and again, sometimes for contracts too small to justify it.

The Standard Selection Questionnaire (SQ)

In September 2016, Procurement Policy Note 08/16 introduced a standard selection questionnaire which, in the government's words, replaced "the current standard Pre-Qualification Questionnaire (PQQ)". It was updated by PPN 03/23, which had to be used by 1 June 2023 at the latest.

The SQ applied to above-threshold procurements under the Public Contracts Regulations 2015 by English public bodies, and by Welsh and Northern Ireland bodies exercising mainly reserved functions. It had three parts:

Part What it covered
Part 1 Basic information about the supplier, such as contact details, group bidding and parent companies
Part 2 Self-declarations about the exclusion grounds
Part 3 Evidence and declarations about economic and financial standing, and technical and professional ability

PPN 03/23 also said that for procurements below the threshold, buyers "must not include a pre-qualification stage", although they could ask proportionate questions about suitability as part of the tender.

You will still see SQs on procurements that started under the old rules before 24 February 2025, and on call-offs from frameworks set up under those rules.

Scotland uses a different form: the Single Procurement Document (Scotland), completed through Public Contracts Scotland. Devolved Scottish public bodies are largely outside the Procurement Act 2023.

What the Procurement Act 2023 uses instead

The Procurement Act 2023 applies to procurements that started on or after 24 February 2025 in England, Wales and Northern Ireland. It splits the old SQ into two parts.

1. Core supplier information on the Central Digital Platform

The general information about your business is entered once on the Central Digital Platform (Find a Tender): basic information, connected persons, qualifications, trade assurances, exclusions and financial information. You share it with each buyer using a share code. See our guide to Central Digital Platform registration.

2. Conditions of participation for each contract

The contract-specific checks are called conditions of participation. Under section 22 of the Act they can relate only to your legal and financial capacity or your technical ability, and they must be proportionate. They are set out in the tender notice and documents. In an open procedure they are usually pass or fail. In a competitive flexible procedure the buyer can also use them to score and shortlist suppliers, which is the nearest thing to the old PQQ stage.

The Cabinet Office guidance sets some useful limits:

The government publishes a standard template called the procurement specific questionnaire (PSQ), and you may see it or a version of it in tender packs. It brings in your core supplier information from the platform and adds questions on exclusions and conditions of participation, filling a similar role to the old SQ.

Industry questionnaires have not disappeared. The guidance confirms that schemes such as Build UK's Common Assessment Standard can still be used for works, as long as they comply with the Act. Main contractors also use their own supply chain questionnaires for subcontractors.

Smaller contracts: no separate pre-qualification stage

For regulated below-threshold contracts, section 85 of the Act stops buyers from restricting who can tender by reference to suitability. In practice that means no separate PQQ or SQ stage before you submit a tender. Buyers can still check things like insurance, experience and finances when they assess tenders.

The Cabinet Office guidance lists the exceptions:

Schools and most Northern Ireland public bodies are outside these below-threshold rules altogether.

After the decision: assessment summaries

The Act also changed what you receive after an above-threshold competition. Before publishing a contract award notice, the buyer must give every supplier whose tender was assessed an assessment summary. It sets out how your tender was assessed and, where different, how the winning tender was assessed. A standstill period of eight working days then usually applies before the contract is signed, giving bidders time to raise concerns.

Assessment summaries are the best free bid training you will get. Compare your scores question by question with the winner's, and use them to improve your standard answers.

What a small firm should prepare

Whatever the questionnaire is called, the same evidence comes up again and again. Keep a folder with current versions of:

Review it every quarter and whenever something changes, and update your Central Digital Platform record at the same time.

Frequently asked questions

Is a PQQ the same as an SQ?

They do the same job. The Standard Selection Questionnaire replaced the standard PQQ in 2016 for above-threshold procurements under the Public Contracts Regulations 2015. Many people still call any selection questionnaire a PQQ.

Do public buyers still use PQQs?

Not under that name for most new procurements in England, Wales and Northern Ireland, which now use the Central Digital Platform and conditions of participation under the Procurement Act 2023. You will still see SQs on procurements started under the old rules, Welsh buyers may use a PQQ stage on smaller contracts, and main contractors often use their own questionnaires.

Can a buyer insist on audited accounts?

Not from a supplier that is not already required to have its accounts audited. Under the Procurement Act 2023 the buyer must accept other evidence of financial standing instead.

What is an assessment summary?

It is the explanation a buyer must give each assessed bidder before publishing a contract award notice on an above-threshold contract. It covers how your tender was scored and, where different, how the winning tender was scored.

What is a procurement specific questionnaire (PSQ)?

It is a standard government template used under the Procurement Act 2023. It pulls in your core supplier information from the Central Digital Platform and asks the contract-specific questions on exclusions and conditions of participation.

Next step: browse open contracts for your trade, or get a free weekly shortlist matched to your firm, with requirements flagged: get free alerts.

This guide is general information, not legal advice.