Subcontracting on public contracts: working for main contractors

Last reviewed 21 October 2026. General guidance, not legal advice.

On this page (8 parts)
  1. Why subcontracting is often the first step
  2. How to find main contractors that have won public work
  3. Your payment rights as a subcontractor
  4. What main contractors usually ask of subcontractors
  5. If you are paid late
  6. Practical steps
  7. Frequently asked questions
  8. Sources

This guide is for small trades and facilities firms that want public sector work but are not ready to bid for whole contracts. It explains how to find the main contractors (tier 1 or prime contractors) that have won public contracts, what they expect from subcontractors, and your payment rights as a subcontractor in England, Wales and Northern Ireland.

Key points

Why subcontracting is often the first step

Many public contracts are let as large, multi-site or multi-service packages, often through frameworks. The firm that wins (tier 1) then buys in specialist trades (tier 2 and below). For a small firm, that can be an easier way in: you price a work package rather than a whole contract, and build a public sector track record for later bids of your own. The trade-off is that you work to the main contractor's terms, so know your payment rights before you sign.

How to find main contractors that have won public work

Since 24 February 2025, notices for new procurements in England, Wales and Northern Ireland above threshold, and below threshold in England and Wales (Welsh notices arrive via Sell2Wales), are published on Find a Tender. Several tell you who won.

On Find a Tender, the Contracts search covers awarded contracts under the Procurement Act 2023, and Opportunities covers pipelines and active tenders. For procurements started under the old rules (the Public Contracts Regulations 2015), use Find a Tender's general search and the "Awarded contract" filter on Contracts Finder, which still carries their award information, including call-offs from older frameworks.

Once you have a name, look for a supplier registration page on the main contractor's website and ask whether it runs supply chain or "meet the buyer" days. See how to find public sector contracts and frameworks, DPS and dynamic markets.

Your payment rights as a subcontractor

The 30-day rule in the Procurement Act 2023

Section 73 of the Procurement Act 2023 implies payment terms into every "public sub-contract", which the Act defines as a contract substantially for the purpose of performing (or contributing to the performance of) all or any part of a public contract. In practice this means:

How far down the chain does it go? Cabinet Office guidance says section 73 "ensures that the payment terms in section 68 are passed on throughout public contract supply chains". So it can cover a tier 3 subcontract as well as tier 2, as long as the contract is substantially for performing the public contract. It does not apply to sub-contracts under concession contracts, utilities contracts awarded by a private utility, or contracts awarded by a school. Section 88 implies the same kind of terms into sub-contracts under regulated below-threshold contracts.

Contracts procured under the Public Contracts Regulations 2015 (started before 24 February 2025) keep the old rule in regulation 113: payment within 30 days of the invoice being regarded as valid and undisputed, passed down to subcontracts.

Construction contracts: the 1996 Act

Part 2 of the Housing Grants, Construction and Regeneration Act 1996 applies to construction contracts for work in England, Wales and Scotland. Some contracts are excluded. Northern Ireland has equivalent rules in the Construction Contracts (Northern Ireland) Order 1997, including adjudication and the right to suspend work.

"Construction operations" include building repair and maintenance, installing heating, lighting, ventilation, power supply, drainage, water supply, fire protection, security and communications systems, and painting and decorating. Cleaning counts only in the course of construction, alteration, repair, extension or restoration, and landscaping only as part of construction operations. Routine cleaning, grounds, pest control or waste contracts may fall outside it, so check before relying on these rights.

Where the Act applies:

Right What the Act says
Stage payments You are entitled to instalment or periodic payments unless the work is specified or agreed to last less than 45 days.
Payment notice The contract must provide for a notice of the sum due no later than 5 days after the payment due date. If the payer fails to give one, you can give your own.
Pay less notice To pay less than the notified sum, the payer must give notice of the lower sum and how it was worked out, by the agreed deadline (in England and Wales, if none is agreed, 7 days before the final date for payment).
No "pay when paid" A clause making your payment depend on the main contractor being paid is ineffective, unless the party further up is insolvent.
Suspension If the notified sum is not paid by the final date, you can suspend any or all of your work after giving at least 7 days' notice stating the grounds.
Adjudication You can refer a dispute at any time. The timetable aims to appoint the adjudicator and refer the dispute within 7 days of your notice, with a decision within 28 days of referral (longer if agreed).

In England and Wales, if your contract does not set a final date for payment, the statutory Scheme for Construction Contracts sets it at 17 days from the date payment becomes due. Where section 73 also applies, a term that overrides the 30-day rule is without effect.

Government policy on how main contractors pay

Procurement Policy Note (PPN) 018 applies to central government departments, their executive agencies and non-departmental public bodies when awarding contracts worth over £5 million a year (including VAT), for procurements advertised on or after 1 October 2025. Bidders that use a supply chain must show they pay at least 95% of invoices within 60 days (90% with an action plan) and pay all invoices within an average of 45 days or fewer, in at least one of the two previous six-month reporting periods. This replaced the earlier 55-day average. Bidders must also confirm they put at least 30-day payment terms in supply chain contracts and require them to be passed down. Other public bodies may choose to apply it.

Under PPN 021, the same bodies should spot check payment in the supply chains of contracts worth over £5 million a year at least once every six months, from 1 October 2025.

What main contractors usually ask of subcontractors

Expect some or all of these:

If you are paid late

  1. Check your invoice has the minimum information and meets any requirements in your subcontract.
  2. Chase in writing, quoting your payment terms and, where it applies, section 73 (or 88) of the Procurement Act 2023.
  3. Consider statutory interest. If your contract does not set its own rate, you can usually claim interest at 8% plus the Bank of England base rate, plus a fixed sum of £40, £70 or £100 depending on the size of the debt.
  4. Use your construction rights if the 1996 Act applies: your own payment notice, suspension on 7 days' notice, or adjudication.
  5. Contact the Public Procurement Review Service (PPRS) using the online form linked from GOV.UK's Procurement Compliance & Oversight page. It handles late payment of valid, undisputed invoices on contracts let by in-scope public bodies, including within the supply chain. You can ask to stay anonymous, and its recommendations are non-binding. It does not cover devolved Welsh or transferred Northern Ireland authorities: for those, GOV.UK points to the Wales Procurement Review Unit and Northern Ireland's Construction and Procurement Delivery. It suspends its involvement if you start legal action, including sending a pre-action letter.
  6. Contact the Small Business Commissioner if you have fewer than 50 staff and your customer has over 50 employees. It is free, covers the whole UK and makes non-binding recommendations. It does not handle construction disputes or work covered by the Housing Grants, Construction and Regeneration Act 1996: use adjudication for those.

See getting paid on public contracts for more.

Practical steps

  1. Look up recent contract details notices and pipelines for two or three public bodies near you.
  2. Note the main contractors that keep appearing for your trade and register on their supplier portals.
  3. Get the accreditations they ask for.
  4. Before signing, read the payment clause: invoice requirements, due dates and dispute process.
  5. Keep every invoice and a record of when it was received.

Frequently asked questions

Does the 30-day rule apply if I work for a subcontractor, not the main contractor?

It can. Section 73 covers any contract substantially for performing the public contract, and Cabinet Office guidance says the terms pass throughout the supply chain.

Can a main contractor put 60-day terms in my subcontract?

If section 73 applies, any term that tries to restrict or override the 30-day term is without effect.

Is my cleaning or grounds contract a "construction contract"?

Only if the work forms part of construction operations, such as cleaning during a refurbishment or landscaping as part of a build.

Ready to look? Browse open contracts for your trade to see who is buying, or get a free weekly shortlist: get free alerts.

This guide is general information, not legal advice.

Sources