Subcontracting on public contracts: working for main contractors
On this page (8 parts)
This guide is for small trades and facilities firms that want public sector work but are not ready to bid for whole contracts. It explains how to find the main contractors (tier 1 or prime contractors) that have won public contracts, what they expect from subcontractors, and your payment rights as a subcontractor in England, Wales and Northern Ireland.
Key points
- Under the Procurement Act 2023, a 30-day payment term is implied into most public sub-contracts (not those under school, concession or private utility contracts), and Cabinet Office guidance says it is meant to flow down to the lower tiers of the supply chain.
- Contract details notices on Find a Tender must name the winning supplier and give its contact details.
- For construction work, the Housing Grants, Construction and Regeneration Act 1996 gives rights to payment notices, adjudication and to suspend work on at least 7 days' notice if unpaid.
- Bidders for contracts over £5 million a year with central government departments, agencies and non-departmental public bodies (not NHS trusts) must show they pay 95% of invoices within 60 days (90% with an action plan) and in an average of 45 days or fewer (procurements advertised from 1 October 2025).
- The Public Procurement Review Service looks at late payment in the supply chains of in-scope public bodies' contracts, though its recommendations are non-binding.
Why subcontracting is often the first step
Many public contracts are let as large, multi-site or multi-service packages, often through frameworks. The firm that wins (tier 1) then buys in specialist trades (tier 2 and below). For a small firm, that can be an easier way in: you price a work package rather than a whole contract, and build a public sector track record for later bids of your own. The trade-off is that you work to the main contractor's terms, so know your payment rights before you sign.
How to find main contractors that have won public work
Since 24 February 2025, notices for new procurements in England, Wales and Northern Ireland above threshold, and below threshold in England and Wales (Welsh notices arrive via Sell2Wales), are published on Find a Tender. Several tell you who won.
- Contract award notice. Published before a public contract is entered into.
- Contract details notice. This must be published within 30 days of the contract being entered into (120 days for light touch contracts). After an open or competitive flexible procedure, it must give each supplier's name, postal and email address, and whether it is a small or medium-sized enterprise (SME).
- Lower value contracts. For regulated below-threshold contracts worth at least £12,000 (central government bodies other than devolved Welsh ones) or £30,000 (other bodies), a contract details notice must be published as soon as reasonably practicable after the contract is entered into.
- Pipeline notices. A public body expecting to pay more than £100 million under its contracts in the coming financial year must publish, within 56 days of the year starting, a pipeline notice of contracts over £2 million it plans to tender in the next 18 months (not required of transferred Northern Ireland authorities). Pipelines let you approach likely bidders early.
On Find a Tender, the Contracts search covers awarded contracts under the Procurement Act 2023, and Opportunities covers pipelines and active tenders. For procurements started under the old rules (the Public Contracts Regulations 2015), use Find a Tender's general search and the "Awarded contract" filter on Contracts Finder, which still carries their award information, including call-offs from older frameworks.
Once you have a name, look for a supplier registration page on the main contractor's website and ask whether it runs supply chain or "meet the buyer" days. See how to find public sector contracts and frameworks, DPS and dynamic markets.
Your payment rights as a subcontractor
The 30-day rule in the Procurement Act 2023
Section 73 of the Procurement Act 2023 implies payment terms into every "public sub-contract", which the Act defines as a contract substantially for the purpose of performing (or contributing to the performance of) all or any part of a public contract. In practice this means:
- Any sum due must be paid before the end of 30 days beginning with the day your invoice is received, or, if later, the day payment falls due under the invoice.
- The 30 days does not apply if the customer considers the invoice invalid or disputes it, but it must tell you without undue delay.
- An invoice is valid if it sets out your name, a description of the goods, services or works, the sum requested and a unique identification number, and meets any other requirement in the contract.
- Any term that tries to restrict or override these terms is without effect. You can still agree to be paid sooner.
How far down the chain does it go? Cabinet Office guidance says section 73 "ensures that the payment terms in section 68 are passed on throughout public contract supply chains". So it can cover a tier 3 subcontract as well as tier 2, as long as the contract is substantially for performing the public contract. It does not apply to sub-contracts under concession contracts, utilities contracts awarded by a private utility, or contracts awarded by a school. Section 88 implies the same kind of terms into sub-contracts under regulated below-threshold contracts.
Contracts procured under the Public Contracts Regulations 2015 (started before 24 February 2025) keep the old rule in regulation 113: payment within 30 days of the invoice being regarded as valid and undisputed, passed down to subcontracts.
Construction contracts: the 1996 Act
Part 2 of the Housing Grants, Construction and Regeneration Act 1996 applies to construction contracts for work in England, Wales and Scotland. Some contracts are excluded. Northern Ireland has equivalent rules in the Construction Contracts (Northern Ireland) Order 1997, including adjudication and the right to suspend work.
"Construction operations" include building repair and maintenance, installing heating, lighting, ventilation, power supply, drainage, water supply, fire protection, security and communications systems, and painting and decorating. Cleaning counts only in the course of construction, alteration, repair, extension or restoration, and landscaping only as part of construction operations. Routine cleaning, grounds, pest control or waste contracts may fall outside it, so check before relying on these rights.
Where the Act applies:
| Right | What the Act says |
|---|---|
| Stage payments | You are entitled to instalment or periodic payments unless the work is specified or agreed to last less than 45 days. |
| Payment notice | The contract must provide for a notice of the sum due no later than 5 days after the payment due date. If the payer fails to give one, you can give your own. |
| Pay less notice | To pay less than the notified sum, the payer must give notice of the lower sum and how it was worked out, by the agreed deadline (in England and Wales, if none is agreed, 7 days before the final date for payment). |
| No "pay when paid" | A clause making your payment depend on the main contractor being paid is ineffective, unless the party further up is insolvent. |
| Suspension | If the notified sum is not paid by the final date, you can suspend any or all of your work after giving at least 7 days' notice stating the grounds. |
| Adjudication | You can refer a dispute at any time. The timetable aims to appoint the adjudicator and refer the dispute within 7 days of your notice, with a decision within 28 days of referral (longer if agreed). |
In England and Wales, if your contract does not set a final date for payment, the statutory Scheme for Construction Contracts sets it at 17 days from the date payment becomes due. Where section 73 also applies, a term that overrides the 30-day rule is without effect.
Government policy on how main contractors pay
Procurement Policy Note (PPN) 018 applies to central government departments, their executive agencies and non-departmental public bodies when awarding contracts worth over £5 million a year (including VAT), for procurements advertised on or after 1 October 2025. Bidders that use a supply chain must show they pay at least 95% of invoices within 60 days (90% with an action plan) and pay all invoices within an average of 45 days or fewer, in at least one of the two previous six-month reporting periods. This replaced the earlier 55-day average. Bidders must also confirm they put at least 30-day payment terms in supply chain contracts and require them to be passed down. Other public bodies may choose to apply it.
Under PPN 021, the same bodies should spot check payment in the supply chains of contracts worth over £5 million a year at least once every six months, from 1 October 2025.
What main contractors usually ask of subcontractors
Expect some or all of these:
- Health and safety accreditation, often from a member scheme of Safety Schemes in Procurement (SSIP), which aims to reduce duplicated health and safety assessments. See SSIP and CHAS.
- Constructionline or a similar pre-qualification service. See council approved lists and Constructionline.
- Insurance at levels the main contractor sets. See insurance and turnover requirements.
- Social value. Central government takes account of social value when awarding many contracts and monitors the winner's commitments, so you may be asked to help deliver them, for example through local jobs or training. See social value in public contracts.
- Cyber security. Under PPN 014, central government requires Cyber Essentials (or equivalent controls) for certain contracts, such as those where suppliers handle citizens' personal information. See Cyber Essentials.
- Trade accreditations for your specific work. See accreditations by trade.
If you are paid late
- Check your invoice has the minimum information and meets any requirements in your subcontract.
- Chase in writing, quoting your payment terms and, where it applies, section 73 (or 88) of the Procurement Act 2023.
- Consider statutory interest. If your contract does not set its own rate, you can usually claim interest at 8% plus the Bank of England base rate, plus a fixed sum of £40, £70 or £100 depending on the size of the debt.
- Use your construction rights if the 1996 Act applies: your own payment notice, suspension on 7 days' notice, or adjudication.
- Contact the Public Procurement Review Service (PPRS) using the online form linked from GOV.UK's Procurement Compliance & Oversight page. It handles late payment of valid, undisputed invoices on contracts let by in-scope public bodies, including within the supply chain. You can ask to stay anonymous, and its recommendations are non-binding. It does not cover devolved Welsh or transferred Northern Ireland authorities: for those, GOV.UK points to the Wales Procurement Review Unit and Northern Ireland's Construction and Procurement Delivery. It suspends its involvement if you start legal action, including sending a pre-action letter.
- Contact the Small Business Commissioner if you have fewer than 50 staff and your customer has over 50 employees. It is free, covers the whole UK and makes non-binding recommendations. It does not handle construction disputes or work covered by the Housing Grants, Construction and Regeneration Act 1996: use adjudication for those.
See getting paid on public contracts for more.
Practical steps
- Look up recent contract details notices and pipelines for two or three public bodies near you.
- Note the main contractors that keep appearing for your trade and register on their supplier portals.
- Get the accreditations they ask for.
- Before signing, read the payment clause: invoice requirements, due dates and dispute process.
- Keep every invoice and a record of when it was received.
Frequently asked questions
Does the 30-day rule apply if I work for a subcontractor, not the main contractor?
It can. Section 73 covers any contract substantially for performing the public contract, and Cabinet Office guidance says the terms pass throughout the supply chain.
Can a main contractor put 60-day terms in my subcontract?
If section 73 applies, any term that tries to restrict or override the 30-day term is without effect.
Is my cleaning or grounds contract a "construction contract"?
Only if the work forms part of construction operations, such as cleaning during a refurbishment or landscaping as part of a build.
Ready to look? Browse open contracts for your trade to see who is buying, or get a free weekly shortlist: get free alerts.
This guide is general information, not legal advice.
Sources
- legislation.gov.uk: Procurement Act 2023, section 68 (checked 21 October 2026)
- legislation.gov.uk: Procurement Act 2023, section 73 (checked 21 October 2026)
- legislation.gov.uk: Procurement Act 2023, section 88 (checked 21 October 2026)
- legislation.gov.uk: Procurement Act 2023, section 50 (checked 21 October 2026)
- legislation.gov.uk: Procurement Act 2023, section 53 (checked 21 October 2026)
- legislation.gov.uk: Procurement Act 2023, section 87 (checked 21 October 2026)
- legislation.gov.uk: Procurement Act 2023, section 93 (checked 21 October 2026)
- legislation.gov.uk: Procurement Regulations 2024, regulation 32 (checked 21 October 2026)
- legislation.gov.uk: Public Contracts Regulations 2015, regulation 113 (as made) (checked 21 October 2026)
- legislation.gov.uk: Housing Grants, Construction and Regeneration Act 1996, section 104 (checked 21 October 2026)
- legislation.gov.uk: Housing Grants, Construction and Regeneration Act 1996, section 105 (checked 21 October 2026)
- legislation.gov.uk: Housing Grants, Construction and Regeneration Act 1996, section 108 (checked 21 October 2026)
- legislation.gov.uk: Housing Grants, Construction and Regeneration Act 1996, section 109 (checked 21 October 2026)
- legislation.gov.uk: Housing Grants, Construction and Regeneration Act 1996, payment sections 110 to 113 (checked 21 October 2026)
- legislation.gov.uk: Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule Part II (checked 21 October 2026)
- legislation.gov.uk: Construction Contracts (Northern Ireland) Order 1997, article 7 (checked 21 October 2026)
- legislation.gov.uk: Construction Contracts (Northern Ireland) Order 1997, article 11 (checked 21 October 2026)
- GOV.UK: Guidance: Electronic Invoicing and Payment (checked 21 October 2026)
- GOV.UK: Guidance: Contract Details Notices (checked 21 October 2026)
- GOV.UK: Guidance: Pipeline Notice (checked 21 October 2026)
- GOV.UK: PPN 018: Taking account of a supplier's approach to payment in the procurement of major contracts (checked 21 October 2026)
- GOV.UK: PPN 018 guidance (checked 21 October 2026)
- GOV.UK: PPN 021: Payment Spot Checks in Public Sub-Contracts (checked 21 October 2026)
- GOV.UK: PPN 019: Update to legal requirements to publish procurement information on Contracts Finder (checked 21 October 2026)
- GOV.UK: PPN 014: Cyber essentials scheme (checked 21 October 2026)
- GOV.UK: PPN 026: The Social Value Model (checked 21 October 2026)
- GOV.UK: Prompt payment policy (checked 21 October 2026)
- GOV.UK: Procurement Compliance & Oversight (checked 21 October 2026)
- GOV.UK: Scope and Remit of the Public Procurement Review Service (PDF) (checked 21 October 2026)
- GOV.UK: Late commercial payments: charging interest and debt recovery (checked 21 October 2026)
- GOV.UK: About us, Small Business Commissioner (checked 21 October 2026)
- Small Business Commissioner: FAQs (checked 21 October 2026)
- Find a Tender (checked 21 October 2026)
- Contracts Finder (checked 21 October 2026)
- SSIP: Safety Schemes in Procurement (checked 21 October 2026)